Installation process and acceptance of the hottest

2022-08-22
  • Detail

Installation process and acceptance of switch socket

2 If the box retracts more than 20mm into the decorative surface, the jacketed box has been added, and there are reliable measures between the jacketed box and the original box. When pulling and inserting, the jacketed box and the panel cannot be pulled out together

3. The indented decorative surface of the box is less than 20mm, and the outer opening has been smoothed with high-grade mortar, and the inner opening has been plastered squarely

4. The wires of the line have been threaded, and the insulation telemetry of each branch has been completed

5. Wall plastering, painting, wallpaper and other interior decoration work have been completed

6. In order to prevent the civil construction from polluting the socket panel, the cement floor, brick floor, terrazzo, marble floor and other works should have been completed

(II). Material requirements

1 The specifications and models of all types of switches and sockets must meet the design requirements, and there should be electrical product certificate. The products must pass the safety certification of CNEEC Product Certification Committee, and the products should bear the safety certification mark (Great Wall mark). One copy of the certificate of conformity and the safety certificate with the same specification and model shall be prepared respectively

2. The plastic (table) plate shall have sufficient strength, be flat, free of bending, warping and deformation, and have a product certificate

3. Each manufacturer's products shall have copies of two approval certificates

4. Imported electrical products must be attached with the quality verification certificate issued by the State Administration for commodity inspection (the verification certificate can replace the product certificate)

(III). Tools and instruments

red pencil, tape measure, level ruler 2.2.1 selection and characteristics of a/d converter a/d converter chips have a wide variety, different performances, great price differences, wire drops, insulating gloves, etc

II. Quality requirements

(I). Main control items

1 When AC, DC or sockets with different voltage levels are installed in the same place, there should be obvious differences, and sockets with different structures, different specifications and non interchangeable must be selected; The matched plugs should be used differently according to AC, DC or different voltage levels

2. The socket wiring shall comply with the following provisions:

(1) single phase two hole socket, the right hole or upper hole facing the socket is connected with the phase line, and the left hole or lower hole is connected with the zero line; Single phase three hole socket, the right hole facing the socket is connected with the phase line, and the left hole is connected with the zero line

(2) the grounding (PE) or neutral (pen) lines of single-phase three hole, three-phase four hole and three-phase five hole sockets are connected to the upper hole. The grounding terminal of the socket is not connected with the zero line terminal. The phase sequence of wiring of three-phase sockets in the same place is consistent

(3) the grounding (PE) or neutral (pen) line is not connected in series between sockets, mainly due to buffer failure

3. Under special circumstances, the socket installation shall comply with the following provisions:

(1) when the power supply of household appliances with electric shock hazard is connected, the socket with switch that can disconnect the power supply shall be used, and the switch shall disconnect the phase line

(2) the sealed protective socket with protective ground wire contact shall be used in wet places, and the installation height shall not be less than 1.5m

4. The installation of lighting switches shall comply with the following provisions:

(1) the switches of the same building and structure adopt the same series of products, with the same on-off position, flexible operation and reliable contact

(2) phase line is controlled by switch; There is no bedside switch with flexible cord led to the bedside in civil residence

5. The installation of ceiling fan shall comply with the following provisions:

(1) the hook of ceiling fan shall be installed firmly, and the diameter of the hook of ceiling fan shall not be less than the diameter of the hanging pin of ceiling fan, and shall not be less than 8mm; Anti vibration rubber pad; The locking parts of the hanging pin are complete and reliable

(2) the height from the ceiling fan blade to the ground shall not be less than 2.5m

(3) the assembly of ceiling fan does not change the angle of fan blade, and the locking parts of fan blade fixing bolts are complete

(4) between the suspenders, the threaded connection between the suspender and the motor, the meshing length is not less than 20mm, and the locking parts are complete and fastened

(5) the ceiling fan wiring is correct, and the fan blade has no obvious vibration and abnormal sound when running

6. The installation of the wall fan shall comply with the following provisions:

(1) the base of the wall fan shall be fixed with nylon plug or expansion bolt; The number of nylon plugs or expansion bolts shall not be less than 2, and the diameter shall not be less than 8mm Fixed firmly and reliably

(2) the protective cover of the wall fan is fastened and fixed reliably. When running, the fan blade and the protective cover are particularly obvious to vibrate and make abnormal sound

(II) general items

1 The installation of sockets shall comply with the following provisions (mandatory provisions):

(1) when safety sockets are not used, the installation height of child activity places such as nurseries, kindergartens and primary schools shall not be less than 1.8m

(2) the concealed socket panel is close to the wall, there is no gap around, the installation is firm, the surface is smooth and tidy, without fragmentation and scratch, and the decorative cap is complete

(3) the installation height of sockets in workshops and test (actual) laboratories shall not be less than 0.3m from the ground; Sockets concealed in special places shall not be less than 0.15m; The installation height of sockets in the same room is the same

(4) the ground socket panel is flush with the ground or close to the ground, and the cover plate is firmly fixed and well sealed

2. The installation of lighting switch shall comply with the following provisions (mandatory provisions):

(1) the installation position of the switch is convenient for operation, the distance between the edge of the switch and the edge of the door frame is 0.15-0.2m, and the height between the switch and the ground is 1.3m; The pull switch is 2-3m high from the ground. When the floor height is less than 3m, the pull switch is not less than 100mm from the top plate, and the pull outlet is vertically downward

(2) the same model is installed in parallel and the same indoor switch is installed at the same height, and the control is orderly without dislocation. The adjacent distance between pull switches installed in parallel shall not be less than 20mm

(3) the concealed switch panel should be close to the wall, with no gap around, installed firmly, and the surface should be smooth, tidy and free of fragmentation. Scratch, decorative cap complete

3. The installation of ceiling fans shall comply with the following provisions:

(1) the coating shall be complete, the surface shall be free of scratches and pollution, and the upper and lower buckles of the boom shall be installed firmly in place

(2) the ceiling fan switches installed in parallel in the same room have the same height, and the control is orderly without dislocation

4. The installation of the wall fan shall comply with the following provisions:

(1) the height from the lower edge of the wall fan to the ground shall not be less than 1.8m

(2) the coating is complete, the surface is free of scratches and pollution, and the protective cover is free of deformation

III. process flow

cleaning → wiring → installation → power on test run

IV. operation process

(I) cleaning

gently remove the remaining ash blocks in the box with a chisel, at the same time, remove other sundries out of the box, and then wipe the dust in the box with a wet cloth

(II) wiring

1 Switch Wiring Regulations: the phase lines of electrical appliances and lamps shall be controlled by switches. When wiring the switch, the wires in the box should be straightened out. After wiring in turn, the wires in the box should be coiled into a circle and placed in the switch box

2. Socket Wiring Regulations:

uneven coating

① single phase two hole socket has two kinds of horizontal and vertical installation. When horizontally installed, the right pole facing the socket is connected to the phase line, and the left pole is connected to the zero line; When installed vertically, the upper pole facing the socket is connected with the phase line, and the lower pole is connected with the zero line

② the grounding or neutral line of single-phase three hole and three-phase four hole should be above

③ when AC, DC or sockets with different voltages are installed in the same place, there should be obvious differences, and their plugs and sockets should be matched, and they cannot be used instead of each other

3. Wiring: leave a maintenance length (15-20cm) for the wires thrown out of the box, cut off the insulation layer, and be careful not to damage the wire core. For example, if there are terminals in the switch and socket, coil the wires on the corresponding terminals of the switch and socket in a clockwise direction, and then tighten the indenter. If there are plug-in terminals in switches and sockets, fold the wire core back and insert it into the round hole wiring terminal (when the hole is allowed to press the double line), and then press it tightly with jackscrews. Note that the wire core must not be exposed

4. Special attention shall be paid during wiring: in order to ensure safety and use function, all kinds of wire connections in the distribution circuit shall not be connected to other branches by means of jacketed crimping at the terminals of switches and sockets

(III) installation of switches and sockets

1 Switch installation regulations

① switches installed in the same building and structure should adopt the same series of products; The position of the switch should correspond to the lamp position; The opening and closing directions of the rocker switch of the same unit project shall be consistent, and the operation shall be flexible and the contact shall be reliable

② the installation position of the switch should be easy to operate, and the distance between the switch edge and the door frame is 0.15-0.2m; If there are no special requirements in the design, the height from the bottom of the toggle switch to the ground is 1.3m; The pull switch is 2-3 meters high from the ground, and the pull outlet should be vertical downward

③ the adjacent distance between pull switches installed in parallel shall not be less than 20mm

④ phase line shall be controlled by switch; It is strictly forbidden to install bedside switches in civil residences

⑤ for safety and convenience, switches for controlling lamps should not be installed above windows, mirror boxes, lockers and behind pipes in any place, and behind single doors. Waterproof porcelain pull switches or protective boxes should be used in dusty and humid places and outdoors; In inflammable, explosive and particularly humid places, switches should be explosion-proof, closed or installed in other places for control

2. Socket installation regulations

① the installation height of the socket shall comply with the design regulations. If there are no regulations in the design, the following requirements shall be met: the socket for concealed installation shall not be less than 0.3m from the ground, and the socket for concealed installation in special places shall not be less than 0.15m. Safety sockets should be used in children's activity places. When using ordinary socket, its installation height should not be less than 1.8m

② when there is a heating pipe above the socket, the distance between them should be greater than 0.2m. When there is a heating pipe below, the distance between them should be greater than 0.3m. If it is inconsistent, it should be shifted or treated technically

③ in order to avoid the interference of AC power supply to TV signal, there should be a distance of more than 0.5m between TV feeder pipe and socket and AC power pipe and socket

④ the floor socket should have a firm and reliable protective cover plate

⑤ in wet places, waterproof and moisture-proof sockets with good sealing should be used. Special sockets should be installed in places with inflammable, explosive gases and dust

3. Installation of switches and sockets:

① concealed installation: according to the wiring requirements, connect the wires thrown out of the box with the panel of the switch and socket, push the switch or socket into the box, align the box eye, and fix it firmly with machine screws. When fixing, make the panel straight and flush with the wall. Those with decorative caps on the mounting holes of the panel shall be installed together

② open installation: first put the wire thrown out of the box through the outlet hole of the plastic table, and then close the plastic table to the wall and fix it on the box or wood brick with screws. If it is open wiring, the hidden wire slot on the wood table should first be in the direction of the wire, and then fix it firmly with screws. After the plastic table is fixed, put the thrown phase line and ground (zero) line out of the wire hole of the switch and socket according to their respective positions, and press the wire firmly according to the wiring requirements. Then stick the switch or socket on the plastic table, align it, and fix it firmly with wood screws. Finally, cover the switch and socket

(IV) power on test run

1 After the installation of switches and sockets, shake the insulation resistance of the primary line by unit and household according to the system and make records before the power transmission test run

2. Power on and test run after the insulation resistance of each branch is qualified through shake test. Carefully check and patrol after power on to check whether the leakage switch is off, whether the socket wiring is correct, whether the panel is horizontal, whether it is polluted, etc. When checking the socket, it is best to use electroscope, which should be checked one by one. If there is a problem, it should be repaired in time after power failure, and records should be made

(V) finished product protection

1 When installing switches and sockets